In 2010, Tanzania was classified as a low-income country with high population and economic growth rates that resulted in steadily increasing demand for electricity. Load shedding and unplanned outages...
Ratings for the Backbone Transmission Investment Project for Tanzania were as follows: outcomes were satisfactory, the risk to development outcome was low, the Bank performance was moderately satisfactory...
The Backbone Transmission Investment Project for Tanzania seeks a restructuring in this report. This Restructuring Paper proposes to extend the closing date of the Backbone Transmission Investment Project...
The objective of the Backbone Transmission Investment Project of Tanzania is to improve the power supply in the north-western part of the country. The project also intends to reduce the duration and frequency...
The objective of the Backbone Transmission Investment Project of Tanzania is to improve the power supply in the north-western part of the country. The project also intends to reduce the duration and frequency...
The development objective of the Backbone Transmission Investment Project for Tanzania is to improve sufficiency, security and reliability of grid based power to business enterprises, households, and large...