This is the Project Completion Report( PCR) of Fourth Buenos Aires Power Project (SEGBA IV) for Argentina which was approved in September1 976. The objective of the project was to help finance expansion...
The project consists of the main elements of SEGBA's investments in transmission lines, substations and distribution facilities in the Greater Buenos Aires region for the years 1977-1981, and the preparation...
The project consists of the main elements of SEGBA's investments in transmission lines, substations and distribution facilities in the Greater Buenos Aires region for the years 1977-1981, and the preparation...
This news release, dated September 23, 1976, announces the World Bank provided Argentina with a loan of 115 million dollars to help finance an electricity transmission and distribution program in the Greater...