Ratings of Partnership for Market Readiness Project for Morocco were as follows: outcome was moderately unsatisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation quality was substantial. Some of the lessons learned include: (i) Gauging the government's readiness for project implementation needs to consider several factors including their previous experience with similar operations, the complexity as well as the current...
更多显示
详细
-
2019/10/27
-
完成执行与成果报告
-
ICR00004794
-
1
-
1
-
2019/11/01
-
Disclosed
-
Implementation Completion and Results Report (ICR) Document - MA-Partnership for Market Readiness - P128654
-
Partnership for Market Readiness