Ratings for the Second Environmental Management and Capacity Building Project for Uganda were as follows: outcomes were moderately unsatisfactory, risk to development outcome was high, Bank performance was unsatisfactory, and Borrower performance was moderately unsatisfactory. Some lessons learned included: the design of a sustainable and result-driven capacity and institution building intervention needs: for projects that are the main support for...
更多显示
详细
-
2013/06/25
-
完成执行与成果报告
-
ICR2148
-
1
-
1
-
2013/09/12
-
Disclosed
-
Uganda - Second Environmental Management and Capacity Building Project
-
Environmental Education and Public Awareness