Ratings for the Emergency Infrastructure Renewal Project (EIRP) for Cote d’Ivoire were as follows: outcome and Bank performance was satisfactory and monitoring and evaluation (M and E) quality was modest. Some lessons learned included: for future operations, more attention needs to be paid to institutional capacity, beyond that of the Project Coordination Unit (PCU). The EIRP was built on lessons learned about the role of adequate implementation arrangements...