Armenia - Irrigation System Enhancement Project (英语)

The overall outcome of the Irrigation System Enhancement Project for Armenia is moderately unsatisfactory, with moderately unsatisfactory Bank performance and modest monitoring and evaluation quality. The Project underwent its mid-term review (MTR) in November 2015 and was subsequently restructured several times. The first restructuring occurred in April 2017, which extended the closing date by approximately one year to June 30, 2018, to catch up...