Croatia - Highway Sector and Emergency Transport and Mine Clearing Projects (英语)

The audit differs from the Implementation Completion Report ratings as follows: the Highway Sector Project (HSP) outcome is rated unsatisfactory contrary to the ICR satisfactory rating, yet concurs with both ratings of likely sustainability, and modest institutional impacts, but downgrades Bank performance from highly satisfactory to satisfactory, and the Borrower performance from satisfactory to unsatisfactory; and, regarding the Emergency Transport...
更多显示

详细

  • 2004/03/30

  • 项目绩效评估报告

  • 28381

  • 1

  • 1

  • 克罗地亚,

  • 欧洲与中亚区,

  • 2010/07/01

  • Croatia - Highway Sector and Emergency Transport and Mine Clearing Projects

  • bridge management system

This document is being processed or is not available.