Ratings for the Thermal Power Project for Ghana were as follows: outcomes were moderately unsatisfactory; the risk to development outcome was substantial; Bank performance was moderately unsatisfactory; and the Borrower performance was moderately unsatisfactory. Some lessons learned included: when technologies in the energy sector are new to a country, the length of the Operations and Maintenance (0&M) contract should extend at least up until the...