Ratings for the Second Phase of Uttar Pradesh Water Sector Restructuring Project for India were as follows: outcome was moderately satisfactory, bank performance was satisfactory, and monitoring and evaluation quality was substantial. Some lessons learned included: procurement and contract management deserve heightened attention in similar interventions with large civil works (particularly in managing multiple high‐value and complex contracts simultaneously)...
更多显示
详细
-
2022/08/02
-
完成执行与成果报告
-
ICR5851
-
1
-
2022/08/05
-
Disclosed
-
India - Second Phase of Uttar Pradesh Water Sector Restructuring Project