Ratings for the Eshteghal Zaiee: Karmondena (EZ-Kar) Project for Afghanistan were as follows: outcome was unsatisfactory, Bank performance was moderately unsatisfactory, and monitoring and evaluation (M and E) quality was substantial. Some lessons learned included: when sharing a project implementation unit (PIU) with other projects, realistically assess the capacity of the PIU and secure adequate positions to avoid overburdening of staff. While synergies...
更多显示
详细
-
2022/08/30
-
完成执行与成果报告
-
ICR5939
-
1
-
2023/04/12
-
Disclosed
-
Afghanistan - Eshteghal Zaiee : Karmondena (EZ-Kar) Project