Ratings for the Emergency Water and Electricity Services Upgrading Project for Guinea-Bissau were as follows: outcome was moderately satisfactory, Bank performance was satisfactory, and monitoring and evaluation (M and E) quality was substantial. Some lessons learned included: a water and energy project can be successfully implemented in a fragility, conflict, and violence (FCV) context through a combination of investments aimed at improving and expanding...
更多显示
详细
-
2025/02/05
-
完成执行与成果报告
-
ICR00110
-
1
-
2025/02/17
-
Disclosed
-
Guinea-Bissau - Emergency Water and Electricity Services Upgrading Project