文件与报告库

Lao - Southern Provinces Rural Electrification Project (英语)

摘要

The overall outcome rating is moderately satisfactory, because of EdL's unsatisfactory financial performance for most of the project's duration and the technical problems. Bank performance was satisfactory, and that of the borrower moderately satisfactory... 更多显示

详细

  • 2008/02/04
  • 42413
  • 1
  • 1
  • 老挝
  • 东亚与太平洋
  • 2010/07/01
  • Disclosed
  • Lao - Southern Provinces Rural Electrification Project
更多显示

下载

英语全部报告

正式文件版本(可能有签字)