文件与报告库

Armenia - Additional Financing for the Electricity Supply Reliability Project : environmental assessment (Vol. 2) : Environmental management plan for rehabilitation and expansion of Haghtanak substation (英语)

摘要

The development objective of the Additional Financing for the Electricity Supply Reliability Project for Armenia is to increase the reliability and capacity of the transmission network. Some of the negative impacts and mitigation measures include: (1)... 更多显示

详细

  • 2014/04/01
  • 环境评价
  • E4525
  • 2
  • 3 (参阅所有文档系列)
  • 亚美尼亚
  • 欧洲与中亚地区
  • 2014/04/07
  • Disclosed
  • Environmental management plan for rehabilitation and expansion of Haghtanak substation
更多显示

下载

英语全部报告

正式文件版本(可能有签字)